ADVERTISEMENT FOR BIDS
DAKOTA COUNTY
FARMINGTON LIBRARY ENTRANCE
RENOVATION
Farmington, Minnesota
Dakota County will receive single prime sealed bids for main entrance and exterior renovation construction located at the Dakota County Farmington Library, 508 Third Street, Farmington, MN until 4:00 p.m. local time on Thursday March 20, 2014 at the office of Facilities Management, Dakota County Administration Center, Room 2500, 1590 Highway 55, Hastings, Minnesota, 55033 at which time bids will be publicly opened and read aloud.
Pre-bid conference and tour will be held at 9:00 a.m. on Thursday March 13, 2014 at the library site in Farmington, MN.
Bid documents including the bid form, drawings and specifications can only be obtained directly from Dakota County; and will be available on or after March 5 , 2014 at the office of Capital Project Management, Room 2600, 1590 Hwy 55, Hastings, MN. 55033. Project Architect is CNH Architects, Apple Valley, MN.
This project includes exterior finish improvements, concrete and electrical work relating to the main entrance and north elevation of the building.

Prevailing wages are required on this project.

Bids must be submitted only on the bid form in the Bid Document - Project Manual. No oral, telegraphic or telephonic bids or modifications will be considered. Submit with each bid a certified check or acceptable bidderÂ’s bond payable to Dakota County in an amount equal to five percent (5%) of the total base bid. The successful bidder is required to furnish satisfactory Labor and Material Payment Bond and Performance Bond each equal to 100% of the total contract amount.
Bids may not be withdrawn within forty-five (45) days after the bid opening. It is anticipated that the Dakota County Board of Commissioners will consider award of the project on April 8, 2014 and reserves the right to accept any bid or to reject any or all bids, or parts of such bids, and waive informalities or irregularities in bidding. Estimated construction cost is $350,000.
OwnerÂ’s contact and representative is Thomas Burrows 651-438-4350; tom.burrows@co.dakota.mn.us
The Owner requires Substantial Completion of the project by August 1, 2014.
2/27-3/13