Sections

Weather Forecast

Close

Farmington ISD 192: Ad for Bids: Area Learning Center 2019 Remodel

Wednesday, May 1, 2019 - 6:09pm

SECTION 00 11 13
ADVERTISEMENT FOR BIDS

AREA LEARNING CENTER 2019 REMODEL
421 Walnut Street
Farmington, Minnesota

Independent School District #192 will receive single prime sealed bids for the Area Learning Center 2019 Remodel project until 2:00 p.m. local time on May 9, 2019 at the Farmington District Office, 20655 Flagstaff Avenue, Farmington, Minnesota, 55024, at which time and place all bids will be publicly opened and read aloud.
Bidding documents, including the Proposal Form, Drawings and Specifications, will be on file at the Minnesota Builders Exchange; McGraw Hill Construction/Dodge Plan Center; Reed Construction; iSqFt Plan Room (St. Paul, MN); and from PlanWell at https://order.e-arc.com/arcEOC/Secures/PWELL_PrivateList.aspx?PrjType=pub
Albert Lea Builders Exchange; Mankato Builders Exchange; Builders Exchange of Rochester; Southwest Builders Exchange (Marshall, MN);
This project includes: Minor interior remodel, new finishes and fixtures, minor exterior site work and miscellaneous building improvements.
American Reprographics Company, 4730 Park Glen Road, St. Louis Park, Minnesota 55416 (952) 697-8800, facsimile (952) 697-8803 will provide complete downloadable sets of the Bidding Documents to prospective bidders and subcontractors. The downloads will be available on or about April 19, 2019. A deposit check in the amount of $25 made out to ARC for each set downloaded via the internet at http://www.e-arc.com/mn/saintlouispark and clicking on the PlanWell icon, then the Public Plan Room icon, select Area Learning Center 2019 Remodel.
Make proposals on the bid forms supplied in the Project Manual. No oral, telegraphic or telephonic proposals or modifications will be considered. Submit with each bid, a certified check or acceptable bidder's bond payable to Independent School District #192 in an amount equal to five percent (5%) of the total bid. The successful bidder will be required to furnish satisfactory Labor and Material Payment Bond, and Performance Bond.
Bids may not be withdrawn within thirty (30) days after the scheduled time of opening bids, without the consent of the Owner. The Owner reserves the right to accept any bid or to reject any or all bids, or parts of such bids, and waive informalities or irregularities in bidding.
The Owner requires Substantial Completion of the project on or before August 16, 2019.
A pre-bid walk through has been scheduled for Thursday, May 2, 2019 at 1:00 PM.
Board of Education
INDEPENDENT SCHOOL DISTRICT #192
04/25/19-5/2/19